Business Risk Management in Uzbekistan: Building a Risk Register for a Small or Mid-Sized Operation

Risk management for a business in Uzbekistan: a likelihood × impact risk register, nine core risks, prevention and fallback plans, owners and quarterly reviews.

Business Risk Management in Uzbekistan: Building a Risk Register for a Small or Mid-Sized Operation

Short answer: a risk register is a table of events that could hurt the business. Each row holds the risk, its likelihood and impact on a 1 to 5 scale, a prevention measure, a fallback plan and one named owner. Likelihood is multiplied by impact, and the highest scores are handled first. The register is reviewed every quarter. The goal is not to remove every threat. It is to see the largest ones early and know exactly what to do if they materialise.

Once a risk has actually hit and the business is at risk of losing cash or customers, a different playbook applies. It is set out in the main guide to business crisis management. This article covers the work you do before that point.

Why risk work belongs in calm periods

A foreign company's early operation in Uzbekistan is usually lean: one distributor, one landlord, one local accountant, one country manager holding most relationships. Efficient, and fragile.

Most owners only think about risk once the blow lands, and then decisions are made in a hurry and at a high price.

In a calm quarter you have options. You can trial a backup supplier, set up automated backups, get a key employee's knowledge written down. All of this is cheap. The same measure on the day of a crisis costs several times more, or is no longer possible at all.

A register needs two things: a one-page table and one hour a quarter.

Scoring a risk: likelihood × impact

Each risk is scored on two questions.

Also read Product Certification in Uzbekistan: Which Goods Need What, Recognition of Foreign Certificates and Digital Marking Business · 10 min

Likelihood — will this happen in the next 12 months?

  • 1 — almost impossible
  • 2 — unlikely
  • 3 — possible
  • 4 — likely
  • 5 — almost certain, or has already happened

Impact — if it happens, how badly does it hurt?

  • 1 — fixed in a day, barely noticed
  • 2 — a week of disruption
  • 3 — a noticeable part of monthly profit is lost
  • 4 — several months of losses, a cash gap
  • 5 — the business stops or faces closure

Multiply the two. The score runs from 1 to 25:

  • 15–25 — Zone: Red; Action: Act this quarter, owner or country manager tracks it personally
  • 8–14 — Zone: Amber; Action: Action plan and owner, checked each quarter
  • 1–7 — Zone: Green; Action: Monitor, no dedicated spend

Do not score alone. Sit down with the heads of sales, warehouse and finance. Each of them knows the threats in their area better than head office does.

Nine core risks for a small or mid-sized business

Start from this list and adapt it to your sector.

  • Dependence on one large customer — Early signal: One buyer accounts for a large share of revenue; Prevention: Steady flow of new accounts, an internal cap on any single customer's share; Fallback plan: Budget version without that customer, list of costs to cut first
  • Single supplier — Early signal: Delays, sudden price jumps; Prevention: Trial a second supplier with a small batch; Fallback plan: Safety stock of critical items, alternative source on file
  • Key person — Early signal: Knowledge sits with one person, customers only call them; Prevention: Document processes, train a deputy; Fallback plan: Named stand-in agreed in advance
  • Cash gap — Early signal: Balance falling several weeks in a row; Prevention: Payment calendar, minimum cash threshold; Fallback plan: Credit line arranged in calm times, payment priority order
  • Exchange rate — Early signal: High import share, local prices fixed in soum for months; Prevention: Price review rule, currency clause in contracts; Fallback plan: Procedure to update the price list quickly
  • Legal or tax change — Early signal: Draft rules published for discussion; Prevention: Accountant and counsel track regulatory news; Fallback plan: Template to estimate the effect on price and margin
  • IT failure and data loss — Early signal: No backups, passwords held by one person; Prevention: Automated backups, restricted access rights; Fallback plan: Tested restore from backup, access list
  • Fire and theft — Early signal: Old wiring, stock-count discrepancies; Prevention: Extinguishers, cameras, key and access rules; Fallback plan: Property insurance, temporary warehouse or site
  • Reputation — Early signal: More negative reviews, slow replies to complaints; Prevention: Response time standard for complaints, quality control; Fallback plan: Short procedure for who responds and how

Three of these risks deserve extra attention. The tool that shows a cash gap weeks in advance is covered in the article on the payment calendar and cash gaps. If the key person is the founder or country manager, the Plan B section of the article on business succession planning explains how to hand over what only they know. Backups, roles and access control are covered in ERP data security.

At an Andijan packaging plant, a business owner tests a box sample with a backup supplier

How to fill in a register row

A plain spreadsheet is enough. Columns:

  1. Risk. One sentence: what could happen.
  2. Cause and early signal. How you will know it is getting closer.
  3. Likelihood, impact, score.
  4. Prevention. The action that lowers the likelihood.
  5. Fallback plan. What happens in the first 48 hours if it materialises.
  6. Owner. One person, not "the sales team".
  7. Deadline and status. When the action is due and whether it is done.

Illustrative example. A manufacturing subsidiary has monthly revenue of 500 million soum. One retail chain orders 200 million soum a month, which is 40% of revenue. Gross margin is 25%. If the chain leaves, the company loses 200 × 0.25 = 50 million soum of gross profit a month. With net profit of 40 million a month, it swings to a loss of 10 million every month.

The register row:

  • Risk: the main retail chain does not renew its contract.
  • Early signal: order volume down two months running, the chain's buyer has changed.
  • Score: likelihood 3, impact 5, total 15. Red zone.
  • Prevention: add 100 million soum a month from other customers by year end, quarterly senior meeting with the chain.
  • Fallback plan: a budget version without the chain is ready, with a list of costs that go first.
  • Owner: commercial director.

The measure is not "keep the customer at any cost" but "reduce dependence on them". The figures are illustrative.

Currency risk: a simple calculation with a clear lesson

If you import goods or raw materials, your cost depends on the exchange rate. Your local selling price is in soum and often stays fixed for months.

Illustrative example. A shipment costs 20,000 US dollars. At the order date the rate is 12,500 soum, so the shipment is 250 million soum. If the rate rises 5% by the payment date, it costs 262.5 million. The difference is 12.5 million soum. With a 15% markup on cost, the expected profit on the shipment was 37.5 million. A third of it goes on the exchange difference.

You cannot remove this risk, but you can manage it:

  • write a rule: if the rate moves more than a set percentage, the price list is reviewed;
  • ask local counsel about a currency clause in long-term contracts;
  • show payment timing and exchange differences as a separate line in the payment calendar.

When insurance makes sense

Insurance does not remove a risk. It moves part of the loss to the insurer. A simple rule: insure losses you could not cover from your own funds, and carry small, frequent losses yourself.

Mandatory cover. Two types apply to most operations, namely any company with employees or vehicles:

  • Employer's liability. The Law "On Compulsory Insurance of Employer's Civil Liability" (No. ZRU-210 of 16 April 2009) requires an employer with staff on employment contracts to insure its liability. The cover pays for harm to an employee's life or health in the course of their work duties.
  • Motor third-party liability. The Law "On Compulsory Insurance of Civil Liability of Vehicle Owners" (No. ZRU-155 of 21 April 2008) requires vehicle owners to insure their liability for harm to other people's life, health or property caused when the vehicle is used.

Depending on your activity, further mandatory requirements may apply. Confirm the full list with local counsel. If your group has a global insurance programme, check separately whether it actually responds to losses in Uzbekistan.

Voluntary cover. Property (fire, flood, theft), cargo, equipment breakdown. Any risk with an impact of 4 or 5 that you could not absorb yourself is a candidate.

Before buying a policy, ask the insurer:

  • ☐ Which events are excluded?
  • ☐ How is a loss valued: market price or after depreciation?
  • ☐ What is the deductible, the part of the loss you keep?
  • ☐ Which documents are required after an incident, and by when?
In a Tashkent carpet warehouse, a technician and the manager inspect a fire extinguisher

Owners and review rhythm

Every risk has an owner. The owner watches the signal, carries out the action and reports status each quarter. The country manager or general manager answers for the register as a whole.

A full review every quarter. 60 to 90 minutes, with this agenda:

  1. Have the actions for every red-zone risk been completed?
  2. What happened during the quarter: was it in the register, did the fallback plan work?
  3. Update the scores: which risks went down, which went up?
  4. New risks: a new product, a new region, a new law.
  5. Three to five actions for next quarter, each with an owner and a date.

Out-of-cycle review. A major customer leaves, the rate moves sharply, a key employee resigns, a new law is adopted. Do not wait for quarter end.

How to fit the quarterly review into a cycle of weekly and monthly meetings is covered in the article on management rhythm.

Your first register in one hour

  • ☐ Book one hour with the people responsible for sales, warehouse, finance and IT.
  • ☐ Start with the nine risks above and add your own.
  • ☐ Score likelihood and impact for each and calculate the total.
  • ☐ For every red-zone risk, write one action and one owner.
  • ☐ For every red-zone risk, write the first three steps of the fallback plan.
  • ☐ Check that mandatory insurance is in place.
  • ☐ Put the next quarterly review in the calendar.

Conclusion

Risk management does not need a dedicated department or complex software. A one-page register, a likelihood and impact score, an owner for every risk and a one-hour review each quarter are enough. The blows that hit most often are one customer, one supplier, one key person and a shortage of cash. Preparing for them in calm times is cheap. Start today with a single step: work out what share of revenue comes from your three largest customers.

Frequently asked questions

Does a small local subsidiary really need a risk register?

More than a large one does. A large group absorbs the loss of one customer or one employee; a small operation in a new market can see its whole plan broken by it within a month. The register is a single table of 10 to 15 rows with a score, an action and an owner. The first version takes an hour or two.

How often should the register be reviewed?

A full review once a quarter. An extra review after any major event: a key customer leaves, a new law is adopted, the exchange rate moves sharply, a key employee resigns. Red-zone risks get a short check every month at the management meeting.

Which insurance is mandatory in Uzbekistan?

Employer's civil liability insurance (Law No. ZRU-210) and motor third-party liability insurance for vehicle owners (Law No. ZRU-155) are mandatory by law. Depending on the activity, other mandatory types may apply. Property, cargo and business interruption cover are voluntary: choose them based on your risk scores and have local counsel review the terms.

How is a risk register different from a crisis plan?

The register works before anything happens: it lowers the likelihood and prepares you for the hit. A crisis plan is how you protect cash, people and customers once the hit has landed. A good fallback plan in the register makes the first days of a crisis much easier.

What are the three biggest risks for your Uzbek operation?

We can walk through your customers, suppliers, key people and cash flow together, then calmly build a first risk register and a fallback plan for every red-zone risk.

Discuss your risks →

Let's work out where to start

Free consultation with a DORA specialist

Message on Telegram

Let's discuss your project

Leave your number and a specialist will get in touch.

Send a request via Telegram

Your details are used only to contact you.